The West Bengal Power Development Corporation Limited
Tender Portal
Search
Tender Portal
Sl.No | WBPDCL Ref No. | TENDER NIT No. | Tender Description | Last date of Sale of Tender Documents | Last Date of Submission of Tender | Download | |
---|---|---|---|---|---|---|---|
7481 | KTPS/10097 | For “Up-gradation/ Renovation for 4 (C, D) AW System, Stg-I of Unit -2 (at 18 Mtr. above U.C.R.# 2) of K.T.P.S. during Overhauling in June-July, 2013â€. | 21-03-2013 | 28-03-2013 | Original | ||
7482 | STPS/10096 | “Making Hard Surface in between area of C.W. Pump House and Cooling Tower unit#5 at STPS†| 16-03-2013 | 20-03-2013 | Original | ||
7483 | SgTPP/10095 | For supply & delivery of PROTECTIVE SUITS, having sound experience and financial capability at SgTPP. | 13-03-2013 | 27-03-2013 | Original | ||
7484 | KTPS/10094 | For Overhauling of Boiler Non-Pressure Parts-2 (Fans, Dampers, Coal Pipe, Coal feeders) of Unit # 2, KTPS in June-July, 2013. | 18-03-2013 | 21-03-2013 | Original | ||
7485 | SgTPP/10093 | For “Providing Fire Safety & Fire Fighting Services at SgTPP (2x300MW)â€. | 08-03-2013 | 20-03-2013 | Original | ||
7486 | SgTPP/10092 | For: “Cleaning and disposal of debris from various sumps, drains and tunnels inside plant area of SgTPP, Murshidabadâ€. | 08-03-2013 | 13-03-2013 | Original | ||
7487 | STPS/10091 | AMC for BOBR unloading, cleaning of pre-crusher and Crusher house zone, and maintenance ( Electrical and Mechanical) jobs at CHP, STPS for 250 MW unit No.5&6 at STPS for 02(Two) years. | 05-03-2013 | 20-03-2013 | Original | ||
7488 | BkTPP/10090 | For “Annual Maintenance Contract of Computer and Printer of BkTPPâ€. | 09-03-2013 | 18-03-2013 | Original | ||
7489 | CORP/10089 | For "Construction of 2 nos. G+7 storied Field Hostel Buildings including Civil, pile foundation, Sanitary & Plumbing, Electrical, Fire Fighting works and installation of lift for both BkTPP Townships and SgTPP Township under The WBPDCL". | 28-02-2013 | 22-03-2013 | Original | ||
7490 | CORP/10088 | For Construction of 2 nos. of Staff Quarters-type ‘D’ at Sagardighi Thermal Power Project Township, Murshidabad, West Bengal under The West Bengal Power Development Corporation Limited. | 28-02-2013 | 18-03-2013 | Original | ||
7491 | SgTPP/10087 | “Expression of Interest†from all competent manufacturers of 6.6 KV Induction motor for supplying 01 number Pulveriser Asynchronous Motor at SgTPP. | 15.03.2013 | Original | |||
7492 | KTPS/10086 | Grinding Elements of 8.5E (9) Coal Mills, | 21-02-2013 | 08-03-2013 | Original | ||
7493 | BkTPP/10085 | For Rate Contract for Rubber Lagging Jobs of Pulleys at CHP (Stage-1 & Stage-2) of BkTPP. | 23-02-2013 | 04-03-2013 | Original | ||
7494 | CORP/10084 | Construction of Plant Roads and Drains on item rate basis for Sagardighi Thermal Power Project, Phase-II Extension Units (2X500 MW) in the District of Murshidabad, West Bengal. | 04-03-2013 | 15-03-2013 | Original | ||
7495 | KTPS/10083 | Annual maintenance contract of ash slurry discharge pipe diversion for various Ash Ponds of KTPS | 01-03-2013 | 06-03-2013 | Original | ||
7496 | KTPS/10082 | Overhauling of Boiler Non-Pressure Parts-1(Air Pre-heater & Air/Flue/Air Ducts) of Unit # 2 at KTPS in June-July 2013 | 04-03-2013 | 07-03-2013 | Original | ||
7497 | KTPS/10081 | Sinking of one (01) no. deep tube well at KTPS Plant. and (Job-2) “Sinking of one (01) no. deep tube well at KTPS Townshipâ€. | 22-02-2013 | 27-02-2013 | Original | ||
7498 | BkTPP/10080 | “Annual Maintenance of private siding at BkTPPâ€. | 19-02-2013 | 26-02-2013 | Original | ||
7499 | SgTPP/10079 | Inside Rubber Lining Removal, Outside Body repairing by replacement of corroded Shell(by 10 mm thickness M.S. Plate), Outside Shell FRP Lining (08 mm) and Inside Rubber Lining (08 mm) of 60 Ton capacity Bulk Acid Storage Tank for Hydrochloric Acid (34%) at C.P.U. | 20-02-2013 | 06-03-2013 | Original | ||
7500 | BkTPP/10078 | (Job-I) Retrofitting and Supply, Installation, Commissioning of 400KV Distance Protection & Auto Reclose Relays and 33KV Distance Protection Relay at BkTPP and (Job-II) Dismantling of Old Hydrogen Generator and Supply, Installation and Commission. | 25-02-2013 | 11-03-2013 | Original | ||
7501 | SgTPP/10077 | Supply and delivery of SPARES FOR ROTARY AIR PRE-HEATER ( Make DEC, CHINA ) for 2x300MW units ( CHINA make ) of SgTPP. | 15-02-2013 | 13-03-2013 | Original | ||
7502 | SgTPP/10076 | HOT VULCANIZATION MACHINE FOR JOINING OF CONVEYOR BELTS. | 13-02-2013 | 27-02-2013 | Original | ||
7503 | BTPS/10075 | For “Repair & Maintenance of ash pond No-1 on the west side at BTPS†| 22-02-2013 | 26-02-2013 | Original | ||
7504 | SgTPP/10074 | For “Supply and Delivery of Spares for Generator Hydrogen Cooler (China make) for 2X 300 MW Unit at Sagardighi TPP†| 20-02-2013 | 13-03-2013 | Original | ||
7505 | SgTPP/10073 | For Manufacturing, Supply and Delivery of Coal Nozzle Tip for 2x300 MW Unit Boiler (China make) at Sagardighi Thermal Power Project | 22-02-2013 | 08-03-2013 | Original | ||
7506 | STPS/10072 | For “Hiring of 01 no. Bus (Model : Ex-showroom, Capacity : 40+1) to ply between STPS Township, Plant etc. for five years under Workshop Department, STPSâ€. | 14-02-2013 | 27-02-2013 | Original | ||
7507 | CORP/10071 | “Raising of Ash Dyke over existing ash pond no. 1 with provision of decantation pond by compacting in layers the ash and earth by using dozers, vibratory rollers, etc and providing sand chimney, filter, rock toe, etc as per technical specification and drawings at STPS, Puruliaâ€. | 18-02-2013 | 25-02-2013 | Original | ||
7508 | STPS/10070 | "Annual maintenance of sewer line, repairing of pits etc. at STPS(T)â€. | 06-02-2013 | 11-02-2013 | Original | ||
7509 | STPS/10069 | Repair and Maintenance of Compound Wall, Main Boundary Wall, tit-bit repairing of gates of different Qtrs. and other ancillary works at STPS(Township). | 06-02-2013 | 11-02-2013 | Original | ||
7510 | BkTPP/10068 | AMC for Mechanical Maintenance Works of Boiler & its auxiliary systems of Unit # 1, 2, 3, 4 & 5 and Operation & Tit-Bit Maintenance of Mill Reject System of Unit #4 & #5 of BkTPP. | 15-02-2013 | 04-03-2013 | Original | ||
7511 | SgTPP/10067 | HOT VULCANIZATION MACHINE FOR JOINING OF CONVEYOR BELTS AT SgTPP | 13-02-2013 | 27-02-2013 | Original | ||
7512 | KTPS/10066 | Annual Rate Contract for Dry Ash Operation of Fly Ash Evacuation system and maintenance of Dry & wet system of Ash handling plant of 6x210 MW Units at KTPS | 21-02-2013 | 27-02-2013 | Original | ||
7513 | STPS/10065 | For (Job-I) Annual Civil maintenance of different type Qtrs. with minor Civil & Structural works at STPS (T)-Gr.I. (Job-II) Annual Civil maintenance of different type Qtrs. with minor Civil & Structural works at STPS (T)- Gr.II. | 06-02-2013 | 12-02-2013 | Original | ||
7514 | BTPS/10064 | Annual Rate Contract for the job of Manual Breaking of Coal Lumps, on Hopper Gratings at CHP Area, BTPS. | 14-02-2013 | 21-02-2013 | Original | ||
7515 | SgTPP/10063 | Maintenance Contract of Boiler & its Auxiliary systems of Unit No. 1&2 of SgTPP (2 x 300MW) | 02-02-2013 | 13-02-2013 | Original | ||
7516 | SgTPP/10062 | “Dismantling of structures including removal of debris to clear the necessary construction area for CW Pipe line and plant Main Road (1414.50E) at Sg.TPP, Murshidabad†| 29-01-2013 | 31-01-2013 | Original | ||
7517 | BkTPP/10061 | For “Repairing and maintenance work of Dyke, Embankment, Drains etc at Ash Pond, BkTPP.†| 28-01-2013 | 05-02-2013 | Original | ||
7518 | CORP/10060 | Invites Expression of Interest (EOI) from the resourceful and experienced companies/agencies/hospitality services/service providers for providing Cafeteria / Canteen service | 00-00-0000 | 24-01-2013 | Original | ||
7519 | KTPS/10059 | Supply of Sulphuric Acid (H2SO4) at KTPS [Commercial Quality, Purity : 98 ±2%, Sp. Gravity: 1.84, IS : 266-1977 (2nd Revision), Quantity: - 1200 M.T.] | 29-01-2013 | 08-02-2013 | Original | ||
7520 | BkTPP/10058 | Roof Treatment Works at BkTPP. | 19-01-2013 | 29-01-2013 | Original |